May 11, 2026
Construction continued across all three Spring Hill Schools bond project sites during the week of May 4-8, according to Newkirk Novak Construction Partners and DLR Group. Spring ...

April 28, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 20–24, with interior mechanical work, exterior envelope sy...

April 10, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 6–10, with interior finishing work advancing at Spring Hil...

March 13, 2026
Elementary Project Update: Week of March 9–13, 2026 Construction continued across Spring Hill Schools elementary bond projects during the week of March 9–13, with crews...

February 20, 2026
Elementary Project Update: Week of Feb. 16-20, 2026 Spring Hill Schools Bond Project – Weekly Construction Update Week of February 16–20, 2026 Construction is moving forward a...

February 17, 2026
Spring Hill Schools Bond Project – Weekly Construction Update Week of February 9–13, 2026 Construction activity continued across all three Spring Hill Schools elementary proje...

February 9, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of Feb. 2–6, with crews advancing structural framing, slab completion and underground uti...

January 30, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of Jan. 26–30, with crews advancing structural, foundation and utility work at all three...

January 22, 2026
Construction activity continued across Spring Hill Schools elementary bond projects during the week of Jan. 19–23, with crews advancing structural, foundation and utility work at ...

January 15, 2026
Construction activity continued across Spring Hill Schools elementary bond projects during the week of Jan. 12–16, with crews advancing site preparation, foundation work and struc...