Construction continues on the career and technical education and commons additions at Spring Hill High School, with this week’s work focused on foundations and underground utilities.
Crews are working on footings and foundations, along with plumbing and electrical installation beneath the future concrete floors in Areas A and B. The first concrete floor slab pour is scheduled to begin Oct. 2.
Next week, crews are scheduled to continue the first slab pour Oct. 5–7 and plumbing and electrical work in Area B Oct. 5–6. A second slab pour is scheduled for Oct. 8–9.
View the weekly report from Newkirk Novak here.