Construction continued across Spring Hill Schools elementary bond projects during the week of June 8-12, with crews focusing on interior finishes, building systems and site improvements as work progressed toward completion.

At Spring Hill Elementary, crews continued installing ceiling tiles and began casework installation throughout the addition. Specialty fixtures and finishes were installed, and fire alarm pre-testing continued. Progress during the week included completion of stair rail installation, classroom signage and electrical outlet installation.

At Prairie Creek Elementary, crews installed acoustical ceiling clouds and continued low-voltage and mechanical, electrical and plumbing trim-out work. Final grading activities were completed around the site, and interior work continued with display case framing and additional finish installations.

At Timber Sage Elementary, crews continued exterior masonry work while advancing interior finishes, including painting, priming, ceiling grid installation and bathroom wall tile work. Work also included storefront installation on the existing building and associated caulking. Interior drywall finishing continued as crews prepared for upcoming flooring, glazing and mechanical system work.

The attached weekly construction report from the district's contractors includes construction updates, schedules and site photos documenting progress at each elementary project location.

The contractor update can be found here.