Construction Update Image

Construction continued on the Spring Hill High School career and technical education (CTE) and commons additions during the week of Oct. 26-30, with crews advancing concrete slab work and preparing for the next phase of structural construction.

In Area A, crews completed concrete slab placement and continued the curing process. Work also included saw cutting the concrete slab as it cured. Meanwhile, crews began preparing the slab in Area B, with concrete placement scheduled during the week.

Looking ahead to the week of Nov. 2-6, structural steel deliveries are scheduled for both Areas A and B on Nov. 2. Steel erection in Area A is expected to begin Nov. 3 and continue through the week, marking the next phase of construction on the additions.

The attached weekly construction report from the district's contractors includes construction updates, schedules and site photos documenting progress at Spring Hill High School.