Construction continued on the Spring Hill High School CTE and commons additions during the week of Oct. 12-16, with crews advancing underground electrical work and preparing for concrete slab placement.
Crews continued installing the remaining underground electrical systems throughout the week. Contractor progress photos documented completed footings and foundations, along with underground electrical installations nearing completion.
Work also included preparations for the first slab-on-grade concrete pour, with activities scheduled to continue into the following week.
The contractor noted that heavy rainfall could result in weather-related delays, although the number of affected construction days had not been determined when the report was prepared.
Looking ahead to the week of Oct. 19-23, crews are scheduled to continue preparations and concrete placement for the first slab-on-grade pour, followed by work on the second scheduled pour.
The attached weekly construction report from the district's contractors includes construction updates, schedules, aerial site photos and additional images documenting progress at Spring Hill High School.
View the weekly report from Newkirk Novak here.
View Past Weekly Reports.