Construction continued on the Spring Hill High School career and technical education (CTE) and commons additions during the week of Nov. 2-6, with crews beginning structural steel installation and advancing foundation work.

Structural steel materials arrived Nov. 2, with installation beginning in Area A on Nov. 4. Crews began setting columns as the framework for the CTE addition started taking shape. Foundation work also began on the commons addition but was temporarily paused Nov. 4 due to rain.

Looking ahead to the week of Nov. 9-13, crews are scheduled to continue structural steel installation in Area A and resume foundation work on the commons addition. Additional work includes underground electrical installation across the road to the greenhouse on Nov. 9, followed by underground plumbing installation Nov. 10-11.

The attached weekly construction report from the district's contractors includes construction updates, schedules and site photos documenting progress at Spring Hill High School.

View the weekly report from Newkirk Novak here.
View Past Weekly Reports.