Construction continued on the Spring Hill High School CTE and commons additions during the week of Oct. 5-9, with crews focusing on underground mechanical, electrical and plumbing systems as the project moved toward additional concrete placement.

Work throughout the week included underground mechanical, electrical and plumbing installations in Area B. Crews also completed surveying work in Area C on Oct. 6 to establish construction reference points for upcoming work.

Joist and decking materials were delivered Oct. 8 in preparation for future structural construction.

Looking ahead, crews are scheduled to complete remaining underground mechanical, electrical and plumbing work and continue preparations for the first slab-on-grade concrete pour.

The attached weekly construction report from the district's contractors includes construction updates, schedules and site photos documenting progress at Spring Hill High School.