October 23, 2026
Construction continued on the Spring Hill High School career and technical education (CTE) and commons additions during the week of Oct. 19-23, with crews advancing underground el...

October 22, 2026
Spring Hill Schools' 2025 bond projects continue to be tracked through financial reports detailing contingency funds, expenditures and remaining balances for elementary school imp...

October 16, 2026
Construction continued on the Spring Hill High School CTE and commons additions during the week of Oct. 12-16, with crews advancing underground electrical work and preparing for c...

October 9, 2026
Construction continued on the Spring Hill High School CTE and commons additions during the week of Oct. 5-9, with crews focusing on underground mechanical, electrical and plumbing...

October 1, 2026
Construction continues on the career and technical education and commons additions at Spring Hill High School, with this week’s work focused on foundations and underground utiliti...

September 25, 2026
Crews continued work on the Spring Hill High School career and technical education (CTE) and commons additions during the week of Sept. 21-25. The contractor reported progress on ...

September 25, 2026
Work continued on the Spring Hill High School career and technical education (CTE) and commons additions during the weeks of Sept. 8-18. Crews advanced the building pads, storm se...

September 24, 2026
Construction continued on the Spring Hill High School career and technical education (CTE) and commons additions during the week of Aug. 31-Sept. 4. Crews moved from site preparat...

September 24, 2026
Construction advanced on the Spring Hill High School career and technical education (CTE) and commons additions throughout August. Crews continued demolition and site preparation,...

September 24, 2026
Spring Hill Schools continued work on projects funded by the voter-approved $60 million bond during July. The district’s July 28 project review covered elementary additions, HVAC ...

June 25, 2026
Work continued on HVAC upgrades at Spring Hill Elementary, Spring Hill Middle School and the Early Childhood Center during the week of June 22-26 as crews advanced mechanical, ele...

June 25, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of June 22-26 as crews completed interior finishes, site improvements and final building...

June 16, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of June 8-12, with crews focusing on interior finishes, building systems and site improve...

June 16, 2026
Work continued on HVAC upgrades at Spring Hill Elementary and Spring Hill Middle School during the week of June 8-12 as crews advanced demolition, structural improvements and mech...

May 11, 2026
Construction continued across all three Spring Hill Schools bond project sites during the week of May 4-8, according to Newkirk Novak Construction Partners and DLR Group. Spring ...

April 28, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 20–24, with interior mechanical work, exterior envelope sy...

April 10, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 6–10, with interior finishing work advancing at Spring Hil...

April 2, 2026
Spring Hill Schools administrators provided the Board of Education with a detailed update March 23 on the progress, budget and design planning tied to the district’s Building Opp...

March 13, 2026
Elementary Project Update: Week of March 9–13, 2026 Construction continued across Spring Hill Schools elementary bond projects during the week of March 9–13, with crews...

March 3, 2026
Bond Update Summary Provided to USD 230 Board of Education Presented Feb. 23, 2026, by Marc Williams, Executive Director of Operations Spring Hill USD 230 remains committed...