
June 25, 2026
Work continued on HVAC upgrades at Spring Hill Elementary, Spring Hill Middle School and the Early Childhood Center during the week of June 22-26 as crews advanced mechanical, ele...

June 25, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of June 22-26 as crews completed interior finishes, site improvements and final building...

June 16, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of June 8-12, with crews focusing on interior finishes, building systems and site improve...

June 16, 2026
Work continued on HVAC upgrades at Spring Hill Elementary and Spring Hill Middle School during the week of June 8-12 as crews advanced demolition, structural improvements and mech...

May 11, 2026
Construction continued across all three Spring Hill Schools bond project sites during the week of May 4-8, according to Newkirk Novak Construction Partners and DLR Group. Spring ...

April 28, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 20–24, with interior mechanical work, exterior envelope sy...

April 10, 2026
Construction crews made steady progress across all three Spring Hill Schools bond project sites during the week of April 6–10, with interior finishing work advancing at Spring Hil...

April 2, 2026
Spring Hill Schools administrators provided the Board of Education with a detailed update March 23 on the progress, budget and design planning tied to the district’s Building Opp...

March 13, 2026
Elementary Project Update: Week of March 9–13, 2026 Construction continued across Spring Hill Schools elementary bond projects during the week of March 9–13, with crews...

March 3, 2026
Bond Update Summary Provided to USD 230 Board of Education Presented Feb. 23, 2026, by Marc Williams, Executive Director of Operations Spring Hill USD 230 remains committed...

March 3, 2026
View the 2.23.2026 meeting agenda on BoardDocs The Spring Hill USD 230 Board of Education met Feb. 23, 2026. Board members Anna Baker, April Horne, Doug Hull, Jon Chitwood, ...

February 20, 2026
Elementary Project Update: Week of Feb. 16-20, 2026 Spring Hill Schools Bond Project – Weekly Construction Update Week of February 16–20, 2026 Construction is moving forward a...

February 18, 2026
Spring Hill USD 230 continues to make steady progress on projects funded through the community-approved Bond 2025 initiative. Construction, planning and financial oversight effort...

February 17, 2026
Spring Hill Schools Bond Project – Weekly Construction Update Week of February 9–13, 2026 Construction activity continued across all three Spring Hill Schools elementary proje...

February 9, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of Feb. 2–6, with crews advancing structural framing, slab completion and underground uti...

January 30, 2026
Construction continued across Spring Hill Schools elementary bond projects during the week of Jan. 26–30, with crews advancing structural, foundation and utility work at all three...

January 22, 2026
Construction activity continued across Spring Hill Schools elementary bond projects during the week of Jan. 19–23, with crews advancing structural, foundation and utility work at ...

January 15, 2026
Construction activity continued across Spring Hill Schools elementary bond projects during the week of Jan. 12–16, with crews advancing site preparation, foundation work and struc...

January 14, 2026
SPRING HILL, Kan. — The Spring Hill Board of Education received a detailed update Monday on the progress of Bond 2025 projects, with district leaders outlining construction time...

January 13, 2026
Spring Hill Schools continued progress on voter-approved bond projects during the week of Jan. 5–9, 2026, with construction activity advancing at Spring Hill Elementary, Prairie C...
